"It doesn't look
good in terms of the schedule. I don't see any
way we are going to make the delivery deadline,"
our project manager said.
He settled back into his chair, a look of resignation
on his face. I was looking at the same data
and coming to the same conclusion. There was
no way we were going to meet schedule requirements,
much less cost or technical performance requirements,
based on the projections we had just reviewed
with the management team. The schedule had steadily
slipped from project kick-off onward, until
now we faced a significant adjustment.
I had just been assigned as the Deputy Project
Manager for a critical Department of Defense
(DOD) project that was based on cutting-edge
technology that had the potential to change
the way U.S. forces engage the enemy on the
battlefield. The project faced critical challenges
of balancing research and development concerns
in untested technology with prototype production
issues concerning numerous components fabricated
by hand for the very first time.
There was no arguing the data. We used a project
management software package that captured every
detail of the project and provided us with a
clear status on every angle of project progression
at the subtask level. The project manager, Mark
White, was recognized as a technically savvy
businessman who possessed encyclopedic knowledge
of every detail, and he could quickly tell you
the status of any task in his comprehensive
project plan. In every senior management briefing,
this guy absolutely shone through as an authority
on how production projects are controlled, and
he always had the right answer at the right
time. Mark had never managed a research and
development project, however, only production
projects with proven technologies. Now we had
hit a deep pothole. It looked like the schedule
would slip at least a month because of undefined
technical production difficulties and slower-than-anticipated
assembly processes.
I looked at the management team. Their body language
clearly communicated the deep funk the project review
had thrown them into and reflected the mood of the project
manager. I began to get angry, wondering what, specifically,
was putting us behind schedule. I decided I needed much
more data than the spreadsheets, projections, and reports
could tell me. The fabrication plant was within an hour's
drive of headquarters. "Mark," I called across the room,
"I'm headed out on a visit to the fabrication facility.
Just gonna go and see what's going on." The project
manager was back at the computer screen, analyzing the
data
one more time as he waved an acknowledgment
in my direction.
The traffic could have been much worse, and I pulled
up to the gate within the hour. I drove to the assembly
building, processed through security, and entered the
main production floor. Impressed by the product sitting
under bright flood lamps, I noticed a curious feeling
surrounding the work area. There was little actual assembly
activity going on, but I saw assemblers in little groups
talking, drinking coffee, and working on paperwork
doing everything but work on the vehicle. I approached
one of the workers and asked, "Where's the foreman?"
After I explained that I was the Deputy Project Manager,
he directed me to a small room off to the side of the
main area.
"I understand you're the foreman here. I'm the new
Deputy, Jon," I said as I sat down in Hank Glaser's
office. As I talked with the foreman, I slowly realized
that he didn't know how important the schedule was and
how our activities affected DOD testing requirements
that would occur after we delivered the product. I explained
the big picture to Hank, covering all the details and
how our project fit into program requirements, as well
as going over what impact our inability to deliver to
schedule would have on other program elements. Hank
now understood the situation and anxiously shared with
me the technical and production issues that had slowed
the project down.
It turns out that there was great concern about
wiring together different systems that were
being fabricated. The complex product gave off
so much heat during operation that the handmade
circuit modules required metal heat sink covers.
But tight tolerances meant that wiring cables
were getting stuck on heat sink covers throughout
the product as the workers attempted to run
cables. I walked around the production floor
with Hank, talking to the workers as we thought
about the issue.
I noticed a small piece of wide-mesh nylon screen sitting
on a worktable. I picked it up, and it felt slippery
between my fingers, stiff and yet flexible. "Hank, would
this stuff work if you attached it over the top of the
heat sinks?" I asked. "It seems pretty flexible and
slippery, but I don't know if it could take the heat,
and I'm not sure how you would be able to attach it
to the heat sinks." Hank's eyes grew wider as he thought.
"You know," he said, "this is pretty unconventional,
but it might work."
That afternoon, Hank sent the nylon screen
over to engineering to be tested, to design
an approach using such a concept, and to see
if there were any better materials that could
be used to overcome the heat sink problem. As
it turns out, engineering conducted heat-dissipation
tests and validated the concept of the nylon
screen, recommending ordering rolls of the very
same material to be attached by heat-resistant
glue to the heat sink covers on all modules
situated under cable run areas.
I returned to the management team and asked
Mark for permission to relocate my duty area
to the fabrication plant. Mark readily agreed,
since he had already been informed of the technical
solution to the heat sink problem. I began delivering
the project management report directly to the
assembly team, giving them access to the same
data that the management team received on a
regular basis. I also helped with the assembly
process, tucking my tie into my shirt and assembling
pieces of the product, even drilling and counter-sinking
different parts. I got to know the team pretty
well, and we laughed and worried and sweated
through the ramp-up to delivery day.
As it turns out, we beat the schedule by two days,
and we came in under budget, even after I had ruined
some parts of the product by counter-sinking them too
deeply with the drill. Leading by example and opening
the lines of communication had done the trick. In the
assembly worker's view, management had taken the time
to come down and work at their level, keeping them informed
every step of the way, giving them the big picture about
where they fit into the overall scheme of things, and
adding outside perspective on a problem they were too
close to to solve. I also received the "Counter-Sinker
of the Year" Award at the company awards luncheon, gently
being chided that we would have come in even more under
budget if I had only known how to counter-sink better.
?
"It doesn't look good in terms of the schedule.
I don't see any way we are going to make the
delivery deadline," our project manager said.
He settled back into his chair, a look of resignation
on his face. I was looking at the same data
and coming to the same conclusion. There was
no way we were going to meet schedule requirements,
much less cost or technical performance requirements,
based on the projections we had just reviewed
with the management team. The schedule had steadily
slipped from project kick-off onward, until
now we faced a significant adjustment.
|